The upgrade project is picking up again following the installation of the new amenities building.

Connecting paths from the amenities building to the carparks have now been constructed and connection works to commission the building are underway.

Other works to be delivered under the project scope include: Solar lighting along the Riverwalk from Pioneer Park through Bila Park to the entrance of Riverglade Caravan Park, new play equipment, installation of new pedestrian bridge between the two Elm Drive carparks and carpark sealing.

Works completed to date include: Click here to see images

  • Nature play spaces

  • Concrete edging around playground areas

  • Rework of walking paths

  • Two new pedestrian bridges

  • New bollards around the Elm Drive carpark

  • Timber platform seating

  • Clean-up of the banks around the pond