Tumbarumba Skatepark & Playground (Creekscape) Upgrades

Share Tumbarumba Skatepark & Playground (Creekscape) Upgrades on Facebook Share Tumbarumba Skatepark & Playground (Creekscape) Upgrades on Twitter Share Tumbarumba Skatepark & Playground (Creekscape) Upgrades on Linkedin Email Tumbarumba Skatepark & Playground (Creekscape) Upgrades link

The project was officially opened on Wednesday 27 March 2023 and the park was abuzz with the sounds of children playing and people chatting. A big thank you to Cycle Tumbarumba members for putting on a delicious afternoon tea. Council worked closely with Cycle Tumbarumba to integrate the bicycle playground into the parks upgrades, resulting in a fantastic outcome.

Stage one included:

  • New amenities building – wheelchair accessible and raised above flood level for cleaning cost-saving
  • Landscaping and concrete terrace seating facing the skatepark and turf mound facing the oval
  • Cycle Playground – new playground incorporating cycle and nature play. Cycle Tumbarumba secured a NSW Government grant and oversaw the building
  • Low maintenance plantings and more seating and picnic tables
  • New playground equipment
  • Sculptures – designed and installed by Snowy Valleys Sculpture Trail

Funding

Through the NSW Government's Public Spaces Legacy Program Council received $650,000 for Tumbarumba Skatepark & Playground (Creekscape) Masterplanning and Upgrade Project.

The project was officially opened on Wednesday 27 March 2023 and the park was abuzz with the sounds of children playing and people chatting. A big thank you to Cycle Tumbarumba members for putting on a delicious afternoon tea. Council worked closely with Cycle Tumbarumba to integrate the bicycle playground into the parks upgrades, resulting in a fantastic outcome.

Stage one included:

  • New amenities building – wheelchair accessible and raised above flood level for cleaning cost-saving
  • Landscaping and concrete terrace seating facing the skatepark and turf mound facing the oval
  • Cycle Playground – new playground incorporating cycle and nature play. Cycle Tumbarumba secured a NSW Government grant and oversaw the building
  • Low maintenance plantings and more seating and picnic tables
  • New playground equipment
  • Sculptures – designed and installed by Snowy Valleys Sculpture Trail

Funding

Through the NSW Government's Public Spaces Legacy Program Council received $650,000 for Tumbarumba Skatepark & Playground (Creekscape) Masterplanning and Upgrade Project.

  • Official opening

    Share Official opening on Facebook Share Official opening on Twitter Share Official opening on Linkedin Email Official opening link
    supporting image

    28 March 2024

    Thanks to everyone who came along to the celebrations in Goldfields Park. It was a wonderful Autumn afternoon, and the park was full of children playing and people chatting. A big thank you to Cycle Tumbarumba members for putting on a delicious afternoon tea. Council worked closely with Cycle Tumbarumba to integrate the bicycle playground into the parks upgrades, resulting in a fantastic outcome.



  • Opening Celebration

    Share Opening Celebration on Facebook Share Opening Celebration on Twitter Share Opening Celebration on Linkedin Email Opening Celebration link
    supporting image

    11 March 2024

    Community members are invited to join Snowy Valleys Council, Cycle Tumbarumba, and Mr Justin Clancy MP for an official ceremony in Tumbarumba’s Goldfields Heritage Park on Wednesday 27 March 2024, to officially mark the successful completion of the $650,000 park upgrade project funded by the NSW Government’s Public Spaces Legacy Program.

    Everyone is welcome to join in the festivities which will include a plaque unveiling, cake-cutting and a BBQ hosted by Cycle Tumbarumba.

  • Project Wrapping Up

    Share Project Wrapping Up on Facebook Share Project Wrapping Up on Twitter Share Project Wrapping Up on Linkedin Email Project Wrapping Up link
    supporting image

    5 February 2024

    Work on the new nature play area is nearing completion. Final works to be delivered under the project scope include landscaping and the installation of new playground equipment.


  • New Amenities Open

    Share New Amenities Open on Facebook Share New Amenities Open on Twitter Share New Amenities Open on Linkedin Email New Amenities Open link
    supporting image

    14 September 2023

    The finishing steps to stage one upgrades at Goldfields Park, Tumbarumba are almost complete. The old toilet block has been demolished and the new amenities are open. More beautification works are being planned for the demolition area in the coming weeks.

    We have already had positive community feedback that the sightlines to the sports oval have been dramatically improved and that there is a general feeling of more openness in the park now.

  • Amenities Build Underway

    Share Amenities Build Underway on Facebook Share Amenities Build Underway on Twitter Share Amenities Build Underway on Linkedin Email Amenities Build Underway link
    supporting image
    17 July 2023
    Construction of the amenities building in Goldfields Park kicked off today. A section of the park, from the pool carpark to the skate park will be closed during construction.

    Other works to be delivered including: installation of more seating and picnic tables, strategically placed lighting around the new amenities building, low maintenance plantings and demolition of existing (old) amenities building.

    With favourable weather conditions, it is anticipated that the new building will be commissioned and opened to the public in the spring. Last month Council received a project timeline extension to December 2023 to accommodate the delays in the delivery of the building.

  • Building Delay

    Share Building Delay on Facebook Share Building Delay on Twitter Share Building Delay on Linkedin Email Building Delay link
    supporting image

    27 March 2023

    The manufacture and delivery of the new prefabricated amenities building has been delayed and is now not expected to be delivered before June. In the meantime, the existing amenities remain open for locals and visitors.

    Work on the project will pick up again once the prefabricated amenities building is delivered including: low maintenance plantings and more seating and picnic tables and demolishment of existing (old) amenities building.

  • Building a Mound!

    Share Building a Mound! on Facebook Share Building a Mound! on Twitter Share Building a Mound! on Linkedin Email Building a Mound! link
    supporting image
    13 October 2022

    Work has started on forming a large, raised mound in preparation for the installation of the new park amenities.

    The mound is situated between the existing amenities and the oval and will enable the new amenities to sit above the low flood levels.

    Once completed and turfed the raised ground will complement the landscape and feature concrete terrace seating.

    The prefabricated new amenities building has been ordered, but due to demand and the battling construction industry delivery is slated for March 2023.

    In the meantime, the existing amenities will remain open for locals and visitors.


  • Bike Playground Opens

    Share Bike Playground Opens on Facebook Share Bike Playground Opens on Twitter Share Bike Playground Opens on Linkedin Email Bike Playground Opens link
    supporting image

    30 September 2022

    The sun came out and the fence came down at the fabulous new Bike Playground in Goldfields Park today.

    The weather made construction challenging and the finishing touches; line marking, play equipment and seating will be completed when the park dries out.

    Congratulations to Cycle Tumbarumba and everyone involved in the build.

    The bike playground is Cycle Tumbarumba project made possible with funding from the NSW Government.

  • Amenities Update

    Share Amenities Update on Facebook Share Amenities Update on Twitter Share Amenities Update on Linkedin Email Amenities Update link
    supporting image

    26 August 2022

    At their August meeting Council resolved to replace the bespoke amenities block (included in the original masterplan) with an "off the shelf" prefabricated style building. It's estimated the prefabricated building could reduce the amenities build by approximately $150,000, savings that would be put into additional stage one improvements.

    Council also resolved to locate the amenities in Goldfield Park at a location to be agreed with the local community and after further discussions with park user groups the new amenities building will remain at the site designated in the Masterplan, in front of the existing amenities.

    Negotiations with potential amenities contractors are now underway.

    The project completion date has been extended until June 2023

  • Bike Playground Underway

    Share Bike Playground Underway on Facebook Share Bike Playground Underway on Twitter Share Bike Playground Underway on Linkedin Email Bike Playground Underway link
    supporting image

    1 August 2022

    (photo used for this update is an example only)

    Work has begun on Tumbarumba’s new Bike Playground at Goldfields Park. The bike playground will feature a mini play road network, which caters for the youngest cyclists learning to ride, scoot or skate. The final design was developed as part of the Goldfields Park Upgrade masterplan, and seeks to complement the existing skate park, playground and pump track.

    Cycle Tumbarumba received $224,000 for the new bike playground in 2019 through Round 3 of the NSW Government’s Stronger Country Communities Fund and is managing the project.

    On completion of the Bike Playground work will begin on the rest of the upgrades.

Page last updated: 02 Aug 2024, 12:11 PM