Building a Mound!

13 October 2022

Work has started on forming a large, raised mound in preparation for the installation of the new park amenities.

The mound is situated between the existing amenities and the oval and will enable the new amenities to sit above the low flood levels.

Once completed and turfed the raised ground will complement the landscape and feature concrete terrace seating.

The prefabricated new amenities building has been ordered, but due to demand and the battling construction industry delivery is slated for March 2023.

In the meantime, the existing amenities will remain open for locals and visitors.


Share Building a Mound! on Facebook Share Building a Mound! on Twitter Share Building a Mound! on Linkedin Email Building a Mound! link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>