Pioneer Park has been buzzing with activity, here's the latest update:
- Rework of the walking path at the river end near the park’s Labyrinth is complete but access to the path remains closed to give the turf time to regenerate.
- Playground areas have been excavated and new concrete edgings, that double as riding paths, have been built around the play spaces.
- All existing play equipment will stay with the addition of a new slide connecting the highest play area to the lower level and the damaged rope climbing castle will be replaced.
- The boulders from the rock circle have been relocated across the path and will form the basis of a nature play area with the addition of local recycled timbers.
- Concrete formwork has been laid for the path that will connect the Elm Drive park entrance to the new toilets (see photo).