Project Update

28 April 2023

Pioneer Park has been buzzing with activity, here's the latest update:

  • Rework of the walking path at the river end near the park’s Labyrinth is complete but access to the path remains closed to give the turf time to regenerate.
  • Playground areas have been excavated and new concrete edgings, that double as riding paths, have been built around the play spaces.
  • All existing play equipment will stay with the addition of a new slide connecting the highest play area to the lower level and the damaged rope climbing castle will be replaced.
  • The boulders from the rock circle have been relocated across the path and will form the basis of a nature play area with the addition of local recycled timbers.
  • Concrete formwork has been laid for the path that will connect the Elm Drive park entrance to the new toilets (see photo).


Share Project Update on Facebook Share Project Update on Twitter Share Project Update on Linkedin Email Project Update link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>