Full Steam Ahead At Pioneer
14 April 2023
Project update - it's been a busy couple of weeks since the project started:
- The banks around the pond have been excavated in preparation for native plantings.
- Playground areas have been excavated in preparation for new edgings.
- Sections of the concrete walking paths have been excavated.
- Walking path at the river end near the labyrinth has been raised about low flood level and re-concreted.
- Large tree from Lions Junction Park Tumut has been relocated to the new nature play section.
The walking path from the Elm Drive carpark to the River Walk is open. Park users are asked to keep an eye out as heavy machinery moves around the site and stay behind the security fencing.
Share Full Steam Ahead At Pioneer on Facebook
Share Full Steam Ahead At Pioneer on Twitter
Share Full Steam Ahead At Pioneer on Linkedin
Email Full Steam Ahead At Pioneer link