Tumbarumba Showground Resurfacing and New Amenities

Share Tumbarumba Showground Resurfacing and New Amenities on Facebook Share Tumbarumba Showground Resurfacing and New Amenities on Twitter Share Tumbarumba Showground Resurfacing and New Amenities on Linkedin Email Tumbarumba Showground Resurfacing and New Amenities link

Consultation has concluded

Our Infrastructure - Provide well maintained safe, vibrant and accessible community spaces and facilities

Background

Snowy Valleys Council secured $1 million in funding from the NSW Government’s Major Projects Infrastructure Fund to undertake a major refurbishment of the Tumbarumba Showground.

The Project

The Tumbarumba community and showground user groups identified the refurbishment as a high priority. The outdated appearance and age of existing facilities no longer serviced or met user needs. Many cold, wet winters had also left the showground in a poor state, with frequent water-logging creating a patchy and uneven playing surface.

The surface upgrade project was completed in October 2019, ground works included removal of the existing playing surface and leveling and reconfiguration of the rugby oval to incorporate a rodeo arena. A drainage and automatic irrigation system has be installed and the new turf has been laid, returning the showground to its former glory.

The new amenities building situated outside the pavilion was open in December 2020. The new modern amenities and change rooms are a welcome improvement for the community. The showground user groups can now look forward to hosting visitors for camp drafts, football matches and major events.

FOLLOW ALONG WITH THE PROJECT'S PROGRESS VIA THE LATEST NEWS UPDATES BELOW

Below: New amenities building.

Above: Fresh turf and new fence at the sportsground.

Our Infrastructure - Provide well maintained safe, vibrant and accessible community spaces and facilities

Background

Snowy Valleys Council secured $1 million in funding from the NSW Government’s Major Projects Infrastructure Fund to undertake a major refurbishment of the Tumbarumba Showground.

The Project

The Tumbarumba community and showground user groups identified the refurbishment as a high priority. The outdated appearance and age of existing facilities no longer serviced or met user needs. Many cold, wet winters had also left the showground in a poor state, with frequent water-logging creating a patchy and uneven playing surface.

The surface upgrade project was completed in October 2019, ground works included removal of the existing playing surface and leveling and reconfiguration of the rugby oval to incorporate a rodeo arena. A drainage and automatic irrigation system has be installed and the new turf has been laid, returning the showground to its former glory.

The new amenities building situated outside the pavilion was open in December 2020. The new modern amenities and change rooms are a welcome improvement for the community. The showground user groups can now look forward to hosting visitors for camp drafts, football matches and major events.

FOLLOW ALONG WITH THE PROJECT'S PROGRESS VIA THE LATEST NEWS UPDATES BELOW

Below: New amenities building.

Above: Fresh turf and new fence at the sportsground.

Consultation has concluded
  • Site preparation underway

    Share Site preparation underway on Facebook Share Site preparation underway on Twitter Share Site preparation underway on Linkedin Email Site preparation underway link
    supporting image

    28 November 2019

    Site preparation got underway today and will include demolition of the existing buildings and the removal of one mature tree.

    The location of the building and the need to remove the tree was decided in conjunction with members from the Tumbarumba Showground user groups. As part of the project two advanced trees will be planted in late autumn.



    You need to be signed in to add your comment.

  • New Amenities Coming

    Share New Amenities Coming on Facebook Share New Amenities Coming on Twitter Share New Amenities Coming on Linkedin Email New Amenities Coming link
    supporting image


    22 November 2019

    It’s all systems go building the new amenities building for the showgrounds; here’s a sneak peek of the building being prefabricated off-site, delivery is expected in the coming weeks.

    The new building will provide more toilets, plus male and female change rooms. The addition of the female change room will be a welcome improvement for visitors attending major events at the showgrounds.

    Click here to view the full story

    You need to be signed in to add your comment.

  • Those New Turf Feels

    Share Those New Turf Feels on Facebook Share Those New Turf Feels on Twitter Share Those New Turf Feels on Linkedin Email Those New Turf Feels link
    supporting image

    25 September 2019

    Laying of new turf at the showgrounds is underway and the ground is looking turf-riffic!

  • Progress continues

    Share Progress continues on Facebook Share Progress continues on Twitter Share Progress continues on Linkedin Email Progress continues link
    supporting image

    20 September 2019

    Upgrade works at the Tumbarumba Showgrounds are progressing well and we recently enjoyed another productive on-site meeting with the showground's local user groups.

    We will be shutting the gates today to ensure the playing surface is not disturbed before we start laying turf next week (weather permitting).



  • Council Seeks Tender for Multiple Building Design and Constructs

    Share Council Seeks Tender for Multiple Building Design and Constructs on Facebook Share Council Seeks Tender for Multiple Building Design and Constructs on Twitter Share Council Seeks Tender for Multiple Building Design and Constructs on Linkedin Email Council Seeks Tender for Multiple Building Design and Constructs link
    supporting image

    22 July 2019

    Snowy Valleys Council is seeking tenders for the design and construction of multiple buildings to be installed at a range of locations across the region.

    The projects include a new amenities buildings at the Tumbarumba Showgrounds.

    The new amenities building at the Tumbarumba Showground will include change rooms, storerooms, a first-aid room and externally accessed toilets.

    Tender applications close on the 9th of August 2019.

    Click here to read more

  • The Showground Must Go on For Tumbarumba

    Share The Showground Must Go on For Tumbarumba on Facebook Share The Showground Must Go on For Tumbarumba on Twitter Share The Showground Must Go on For Tumbarumba on Linkedin Email The Showground Must Go on For Tumbarumba link
    supporting image

    08 March 2019

    Representatives from Tumbarumba Showground user groups recently met with Council’s project managers and agreed to move forward quickly on the planned major redevelopment of the facility.

    Ten representatives from Tumbarumba Rodeo, Zone 20 Pony Club, Tumbarumba PA&H Society, Tumbarumba Batlow Rugby League Football Club and Tumbarumba Batlow Minor League were invited to view the concept plan for the proposed upgrade of the Tumbarumba Showground playing surface, irrigation and facilities.

    Read more...

    You need to be signed in to add your comment.

  • Showground stakeholder consultation continues

    Share Showground stakeholder consultation continues on Facebook Share Showground stakeholder consultation continues on Twitter Share Showground stakeholder consultation continues on Linkedin Email Showground stakeholder consultation continues link
    supporting image

    Tumbarumba showground users are in continuing talks with Council regarding options for the refurbishment of the Showgrounds.

    Two options are being explored:

    1. Development and construction of new amenities and grandstand plus the reconstruction of the playing surface or

    2. Refurbishment and upgrade of existing amenities and grandstand plus the reconstruction of the playing surface

    Both options are currently being discussed and cost estimates progressed.