Talbingo Dam Boat Ramp Area Improvements

Share Talbingo Dam Boat Ramp Area Improvements on Facebook Share Talbingo Dam Boat Ramp Area Improvements on Twitter Share Talbingo Dam Boat Ramp Area Improvements on Linkedin Email Talbingo Dam Boat Ramp Area Improvements link

Consultation has concluded

The new Talbingo boat ramp with mooring pontoon opened to the public in October 2021. Flocks of day trippers have been enjoying the new swimming area with its grassy banks and picnic facilities over the summer holidays.

The facility allows boat enthusiasts to continue to use Talbingo Dam while swimmers have a safe and friendly recreation area to keep cool. Also included in the project were new amenities, improved pedestrian access and car parking.

The project was managed by Snowy Valleys Council on Snowy Hydro land at Talbingo Reservoir and Snowy Hydro own the facility.

Co-funding of $1,350,000 was awarded for the design and construction of the Talbingo Dam Boat Ramp Area Improvements. Funding of $850,000 was awarded from Department of Planning Industry and Environment (DPIE) and Snowy Hydro contributed $500,000.

Holiday crowds enjoying the few facilities.




The new Talbingo boat ramp with mooring pontoon opened to the public in October 2021. Flocks of day trippers have been enjoying the new swimming area with its grassy banks and picnic facilities over the summer holidays.

The facility allows boat enthusiasts to continue to use Talbingo Dam while swimmers have a safe and friendly recreation area to keep cool. Also included in the project were new amenities, improved pedestrian access and car parking.

The project was managed by Snowy Valleys Council on Snowy Hydro land at Talbingo Reservoir and Snowy Hydro own the facility.

Co-funding of $1,350,000 was awarded for the design and construction of the Talbingo Dam Boat Ramp Area Improvements. Funding of $850,000 was awarded from Department of Planning Industry and Environment (DPIE) and Snowy Hydro contributed $500,000.

Holiday crowds enjoying the few facilities.




Consultation has concluded
  • Picnic shelters complete project

    Share Picnic shelters complete project on Facebook Share Picnic shelters complete project on Twitter Share Picnic shelters complete project on Linkedin Email Picnic shelters complete project link
    supporting image

    16 February 2022

    Works at the Talbingo Dam Boat Ramp and Beach are now complete following the installation of the new picnic shelter.

  • Talbingo Beach looking Turf-rrific

    Share Talbingo Beach looking Turf-rrific on Facebook Share Talbingo Beach looking Turf-rrific on Twitter Share Talbingo Beach looking Turf-rrific on Linkedin Email Talbingo Beach looking Turf-rrific link
    supporting image

    24 December 2021

    The turf has been rolled out and the new Talbingo Beach and swimming area is looking a treat, ready to welcome the summer visitors. If you are heading up for swim or maybe some fishing, be safe and take care.

  • New Talbingo beach

    Share New Talbingo beach on Facebook Share New Talbingo beach on Twitter Share New Talbingo beach on Linkedin Email New Talbingo beach link
    supporting image

    15 November 2021

    Structure for the beach and swimming section is developing nicely.

    Check out these drone images.


  • Great progress at Talbingo Boat Ramp

    Share Great progress at Talbingo Boat Ramp on Facebook Share Great progress at Talbingo Boat Ramp on Twitter Share Great progress at Talbingo Boat Ramp on Linkedin Email Great progress at Talbingo Boat Ramp link
    supporting image

    28 October 2021

    Great progress has been made on the Talbingo Boat Ramp Project over the past week. Favourable weather conditions have allowed for lower-level civil works to progress, including widening of the boat ramp (two lane) and installation of the lower benched structures for the beach.

    The pontoon is complete and open to the public. If you are in the area, please take care around the busy construction site, thanks for your help.


    Boat ramp wideningBoat ramp widening



  • Work continues

    Share Work continues on Facebook Share Work continues on Twitter Share Work continues on Linkedin Email Work continues link
    supporting image

    14 September 2021

    Wetter than average winter and early spring conditions are challenging construction at the Talbingo Boat Ramp, however high level works are continuing and include:

    • Concreting
    • Rip-rap (rock) installation
    • Pontoon installation


    Mid-level works will continue over the next couple of weeks.

  • First concrete pour

    Share First concrete pour on Facebook Share First concrete pour on Twitter Share First concrete pour on Linkedin Email First concrete pour link
    supporting image

    27 August 2021

    Formwork and boxing has been built ready for the first concrete pour today.

    Installation of the pontoons will commence in the next week and should take about a week to install, weather permitting.

  • On-site construction underway

    Share On-site construction underway on Facebook Share On-site construction underway on Twitter Share On-site construction underway on Linkedin Email On-site construction underway link
    supporting image

    6 August 2021

    Preliminary works have commenced on the Talbingo Boat Ramp upgrade and Beach Project this week. Works include site set up, installation of safety fencing, removal of shelters and above waterline excavation.

    The off-site pontoon fabrication has been completed and the parts are ready for delivery to site for installation. The pontoon will be installed adjacent to the boat ramp upon completion of the concrete abutment structure.

    We are working closely with Snowy Hydro to ensure effectiveness on-site as much of the work needs to be undertaken at low-water level and these opportunities are rare given the operational nature of the dam and ongoing wet weather.

    The project also faces challenges due to current COVID-19 restrictions.

  • Offsite pontoon construction

    Share Offsite pontoon construction on Facebook Share Offsite pontoon construction on Twitter Share Offsite pontoon construction on Linkedin Email Offsite pontoon construction link
    supporting image

    April 2021

    Offsite fabrication of the new mooring pontoon is underway. The pontoon will be installed adjacent to the boat ramp upon completion of the concrete abutment structure.

    The majority of onsite construction work on this project needs to be undertaken at low-water level, therefore current high-water levels may delay the project.

    Onsite construction is scheduled to commence in late July 2021.

  • Community consultation

    Share Community consultation on Facebook Share Community consultation on Twitter Share Community consultation on Linkedin Email Community consultation link
    supporting image

    26 November 2020

    A community consultation drop-in session is being held at the Talbingo Shopping Centre on Monday 30 November.

    Come and view the plans, meet the project manager and designer and give us your feedback.

    The pop-up stall will be set up from 3:30-6:30pm.


  • Talbingo boating enthusiasts and tourists to benefit thanks to Government funding

    Share Talbingo boating enthusiasts and tourists to benefit thanks to Government funding on Facebook Share Talbingo boating enthusiasts and tourists to benefit thanks to Government funding on Twitter Share Talbingo boating enthusiasts and tourists to benefit thanks to Government funding on Linkedin Email Talbingo boating enthusiasts and tourists to benefit thanks to Government funding link
    supporting image

    12 March 2020

    Joint media release with NSW Deputy Premier John Barilaro

    Boating enthusiasts, tourists and locals will be able to keep cool and enjoy improved recreational facilities at the Talbingo Dam boat ramp with $1.35 million locked in to create a designated swimming area, improved boating facilities, picnic areas, carparking and foreshore access.

    Deputy Premier and Minister for Regional NSW John Barilaro said the NSW Government committed $850,000 and Commonwealth-owned Snowy Hydro Limited’s $500,000, which will deliver significant improvements south of the existing boat ramp, including a protected swimming area.

    “Safety concerns with the existing swimming area at the spillway on Talbingo Dam will see a transition to the spillway being closed to the public and we have worked closely with Snowy Hydro Limited to identify a suitable alternative that will ensure many tourists and locals continue to visit this great part of NSW,” Mr Barilaro said.

    “I know the community has been vocal about this closure and the impact it will have during the summer months when up to 1,500 people visit the area, which is why I am pleased that the NSW Government is making this happen.

    “The new facilities will allow boats to continue using Talbingo Dam while swimmers will have a safe and friendly environment and I thank Snowy Hydro Limited for its contribution towards this wonderful community recreation area.”

    Minister for Energy and Emissions Reduction Angus Taylor said it’s great for Snowy to be a part of a project that will provide better recreational facilities for the Talbingo community and visitors to the region.

    ”This locally driven initiative will enrich the Talbingo community and importantly, the town’s tourism economy as it recovers from the impact of this summer’s bushfires,” Mr Taylor said.

    Snowy Hydro’s CEO Paul Broad said Snowy is a big supporter of the communities in which we live and work right across the Snowy Mountains and it was important to be part of this project.

    “We have a long and shared history with the Talbingo community. It is one of the original towns built with the Snowy Scheme and it sits on the doorstep of Tumut 3 Power Station,” Mr Broad said.

    Snowy Valleys Council Mayor James Hayes thanked the NSW Government and Snowy Hydro Limited for making the project a reality.

    “Talbingo Dam is much loved by locals and this is a fantastic example of how local government, the NSW Government and Snowy Hydro Limited are working together to make a positive difference to a community” Mr Hayes said.

    Works will commence in 2020 and are expected to be completed before next summer.