The Project
Stage 2 of the Khancoban Pool upgrades include new amenities with toilets, shower, disabled access, canteen, entry area and office, a new fence around the pool facility and the installation of solar heating and a blanket system to help regulate water temperature.
The new amenities building is located at the opposite end of the pool to the old building to enable ramp access and disabled entry parking.
Due to popular demand the old amenities building wasn't demolished as per initial scope of works. The building has been fitted out with a new toilet to facilitate the park and solar panels for the pools solar heating system were installed on the roof. The upgrades were completed prior to the 2023/24 swim season.
Funding
Snowy Valleys Council received $600,000 for Stage 2 of the Khancoban Pool Upgrades from the Bushfire Economic Recovery Funding Round 2 which is jointly funded by the Australian and New South Wales governments.
Stage one of the pool upgrade was completed in 2017 and included building a new 25 metre pool with disability access and a toddler’s pool. The $685,000 project was supported by a $215,000 National Stronger Regions grant, along with a healthy funding injection from Snowy Valleys Council and various Khancoban community groups.
The Project
Stage 2 of the Khancoban Pool upgrades include new amenities with toilets, shower, disabled access, canteen, entry area and office, a new fence around the pool facility and the installation of solar heating and a blanket system to help regulate water temperature.
The new amenities building is located at the opposite end of the pool to the old building to enable ramp access and disabled entry parking.
Due to popular demand the old amenities building wasn't demolished as per initial scope of works. The building has been fitted out with a new toilet to facilitate the park and solar panels for the pools solar heating system were installed on the roof. The upgrades were completed prior to the 2023/24 swim season.
Funding
Snowy Valleys Council received $600,000 for Stage 2 of the Khancoban Pool Upgrades from the Bushfire Economic Recovery Funding Round 2 which is jointly funded by the Australian and New South Wales governments.
Stage one of the pool upgrade was completed in 2017 and included building a new 25 metre pool with disability access and a toddler’s pool. The $685,000 project was supported by a $215,000 National Stronger Regions grant, along with a healthy funding injection from Snowy Valleys Council and various Khancoban community groups.
Share Old Building To Stay on FacebookShare Old Building To Stay on TwitterShare Old Building To Stay on LinkedinEmail Old Building To Stay link
27 July 2023
Due to popular demand the old amenities building will stay. The building will be fitted out with a new toilet to facilitate the park and a new roof will be installed to house solar panels. Solar will also be installed on the roof of the new amenities building.
Share Pool Opens! on FacebookShare Pool Opens! on TwitterShare Pool Opens! on LinkedinEmail Pool Opens! link
12 January 2023
Khancoban Pool opening today, Thursday 12 January with temporary toilet facilities. While we finish off the final items on the new amenity buildings, we have come up with a temporary solution to allow locals to use the pool.
Share Pool To Open In The New Year on FacebookShare Pool To Open In The New Year on TwitterShare Pool To Open In The New Year on LinkedinEmail Pool To Open In The New Year link
20 December 2022
Upgrades works at the Batlow and Khancoban pools have been delayed due to wet weather and will not be completed prior to the Christmas break.
Both pools are now slated to open in mid-January 2023.
Share New Amenities On The Way on FacebookShare New Amenities On The Way on TwitterShare New Amenities On The Way on LinkedinEmail New Amenities On The Way link
25 October 2022
Onsite works to prepare footings and plumbing connections are almost complete and the new amenities building is scheduled to arrive in early November
Connections are expected to take 2 weeks and we will be working hard to open the pool before the end of the month.
Photo left: Offsite building construction progress from 10/10/22.
Share New Amenities Coming Soon on FacebookShare New Amenities Coming Soon on TwitterShare New Amenities Coming Soon on LinkedinEmail New Amenities Coming Soon link
2 June 2022
On-site works to demolish the existing amenities building will get underway soon.
A contract has been awarded for the construction of the new amenities building and we are in the final design stage. The building will be constructed off-site and local trades will be utilised where possible during the installation and commissioning stage.
The current amenities are no longer suitable, safe or secure for residents, and are not compliant with accessibility standards.
Share Contractor negotiations underway on FacebookShare Contractor negotiations underway on TwitterShare Contractor negotiations underway on LinkedinEmail Contractor negotiations underway link
1 March 2022
At the February Ordinary Council meeting Council resolved to not accept any of the tenders received for the Design and Construction of the new amenities building.