Brindabella Road Future Plan

Share Brindabella Road Future Plan on Facebook Share Brindabella Road Future Plan on Twitter Share Brindabella Road Future Plan on Linkedin Email Brindabella Road Future Plan link

Consultation has concluded

Our Infrastructure - provide and partner with other agencies to deliver an effective and safe local transport nextwork

The Project

To survey and design a 10.6km section of the Brindabella Road within the Snowy Valleys Council LGA.

$308,000 was allocated through the Stronger Communities Major Infrastructure Fund to engage external consultants to review and update an existing economic feasibility study to determine benefits of a road upgrade, and to obtain a cost estimate for the design of the major upgrade of the road section from Piccadilly Circus to the Goodradigbee bridge.

The design brief includes options to manage road safety through widening, sealing, and provision of guardrails, stormwater drainage, slope stability and improving environmental impacts.

It is expected that this important piece of survey and design work, along with updated costings, will provide the basis for a funding/treatment model for the unsealed section of road.

Council is actively pursuing funding opportunities for upgrading the road, noting its significance as a tourist link between Canberra and the Snowy Valleys

Our Infrastructure - provide and partner with other agencies to deliver an effective and safe local transport nextwork

The Project

To survey and design a 10.6km section of the Brindabella Road within the Snowy Valleys Council LGA.

$308,000 was allocated through the Stronger Communities Major Infrastructure Fund to engage external consultants to review and update an existing economic feasibility study to determine benefits of a road upgrade, and to obtain a cost estimate for the design of the major upgrade of the road section from Piccadilly Circus to the Goodradigbee bridge.

The design brief includes options to manage road safety through widening, sealing, and provision of guardrails, stormwater drainage, slope stability and improving environmental impacts.

It is expected that this important piece of survey and design work, along with updated costings, will provide the basis for a funding/treatment model for the unsealed section of road.

Council is actively pursuing funding opportunities for upgrading the road, noting its significance as a tourist link between Canberra and the Snowy Valleys

Consultation has concluded
  • Preliminary design presented

    Share Preliminary design presented on Facebook Share Preliminary design presented on Twitter Share Preliminary design presented on Linkedin Email Preliminary design presented link
    supporting image

    Work on the Brindabella Road survey and design continues to move forward. In early September our Assets team met with the contractor for presentation and discussion of the preliminary design.


    You need to be signed in to add your comment.

  • Survey Underway

    Share Survey Underway on Facebook Share Survey Underway on Twitter Share Survey Underway on Linkedin Email Survey Underway link
    supporting image

    Design of the Brindabella Road has kicked off in earnest with the surveyor, geotechnical engineer and environmental consultant now onsite. A small excavator was also mobilised to start taking geotech samples, and the initial environmental walk through was completed.

  • Model Concept Flyover Video

    Share Model Concept Flyover Video on Facebook Share Model Concept Flyover Video on Twitter Share Model Concept Flyover Video on Linkedin Email Model Concept Flyover Video link
    supporting image

    Our external contractor has put together a model concept flyover video of the new road. The video shows an overlay of the new proposed road profile on a 3D contoured photographical image of the Brindabella ranges.
    Check it out here https://youtu.be/ktca2BrrkOo

  • Council Seeks Tender for Survey and Design of Brindabella Road Upgrade

    Share Council Seeks Tender for Survey and Design of Brindabella Road Upgrade on Facebook Share Council Seeks Tender for Survey and Design of Brindabella Road Upgrade on Twitter Share Council Seeks Tender for Survey and Design of Brindabella Road Upgrade on Linkedin Email Council Seeks Tender for Survey and Design of Brindabella Road Upgrade link

    Snowy Valleys Council is seeking tenders from suitably qualified and experienced contractors for the survey and design of a 10.6km section of the Brindabella Road within the Snowy Valleys Council LGA.