Rain Dampens Progress

24 October 2022

Continuous wet weather has hampered the works schedule on the new Batlow learn-to-swim pool and this year's pool season will be delayed. We are working hard to open the pool for the Christmas school holidays.

The learn-to-swim pool is nearing completion, tiling of the pool shell is almost finished and handrails have been installed. The new plant room has been built and the roof is up, allowing for some undercover work to be finalised. Water toys in the splash zone will be installed in the coming weeks.

The new amenities building is scheduled to arrive in early November, and work to connect buildings to utilities will be fast tracked. Final upgrade works include a new shade structure, concrete paths and rehabilitation of the lawn area.