Share December Update on Facebook
Share December Update on Linkedin
Email December Update link
Tumut Aerodrome Reopens
The Tumut Aerodrome officially reopened and returned to full operational status on Friday, 19 December, following the practical completion of Stage 1 of a major aerodrome expansion and upgrade project.
The $12.5 million upgrade, fully funded through the Australian Government’s Bushfire Local Economic Recovery Fund, has transformed the aerodrome into a safer, more reliable facility that better supports firefighting and aeromedical services, particularly during times of natural disaster.
Read more
Share November Update on Facebook
Share November Update on Linkedin
Email November Update link
12 November 2025
Due to recent adverse weather conditions and material supply delays, the full re-opening of the Tumut Aerodrome has been rescheduled to mid December 2025, subject to suitable weather conditions.
An updated NOTAM has been issued to reflect this revised timeline.
We appreciate the community’s patience and understanding as we work to safely finalise the remaining works and deliver a high-quality outcome for all aerodrome users.
Share September Update on Facebook
Share September Update on Linkedin
Email September Update link
11 September 2025
The limited re-opening of the unsealed runway has been extended until 9pm on Monday, 6 October 2025, while we wait for warmer conditions required to complete the works.
The revised date for a full re-opening is now 21 November 2025, dependent on suitable weather for the final sealing stage.
We appreciate your patience as we finalise the works.
Share August Update on Facebook
Share August Update on Linkedin
Email August Update link
26 August 2025
The Tumut Aerodrome will be soft re-opening on Friday, 29 August at 8am.
At this stage, the runway is still unsealed, so it will only be open to smaller aircraft with a maximum take-off weight of 600kg.
The runway will close again on 15 September so crews can finish paving and sealing works. If all goes to plan, the aerodrome will fully re-open to all aircraft on 14 November 2025.
Thanks for your patience while these upgrades are completed!
Share Extension of Runway Closure on Facebook
Share Extension of Runway Closure on Linkedin
Email Extension of Runway Closure link
16 July 2025
The planned soft opening scheduled for 16 July has had to be delayed by a further two weeks due to more recent wet weather.
The 31st of July is now the targeted date for a soft reopening, weather permitting. The soft re-opening will allow limited use of the upgraded aerodrome, gravel runways and taxiways.
The final seal coat is still scheduled for September – October when the weather warms up.
Share Construction Update on Facebook
Share Construction Update on Linkedin
Email Construction Update link
14 May 2025
Construction at the aerodrome is tracking well. Grading works on the main runway and apron are nearly finished, and all drainage around the runways and taxiways is complete.
A temporary finish to the main runway is planned for late June, allowing the aerodrome to become operational. The final sealing works to the main runway, aprons and taxiways will be applied in spring, once warmer temperatures return.
Ground lighting is nearing completion, with inground lighting to follow. Perimeter fencing works will also begin shortly.
Share Key Infrastructure Improvements Progressing on Facebook
Share Key Infrastructure Improvements Progressing on Linkedin
Email Key Infrastructure Improvements Progressing link
19 March 2025
Work commenced in January 2025, beginning with essential site preparations, including services relocation, geotechnical sampling, and the establishment of access points, site compounds, and stockpile areas.
Progress has since advanced to key infrastructure improvements, including:
- Property acquisition negotiations for the land that the southern parallel taxiway will be built on - the southern parallel taxiway is a key component of the aerodrome upgrade that will significantly increase the operational capacity of the aerodrome during fire fighting emergencies.
- Construction of a new RFS Hardstand – improving firefighting readiness
- Runway widening and pavement reconstruction – enhancing aircraft maneuverability
Additional works include upgrades to the General Aviation (GA) Apron, Taxiway A3, and modifications to Taxiway A2 and its connections.
For the safety of all users, the area is closed to aircraft during construction. All stakeholders have been directly notified to ensure minimal disruption.
Once complete these improvements will position Tumut Aerodrome as a key hub for emergency response and aviation operations, ensuring long-term benefits for the community and the broader region.
Share Works Underway on Facebook
Share Works Underway on Linkedin
Email Works Underway link
24 February 2025
Construction is underway at the Tumut Aerodrome, starting with the extension of the southern parallel taxiway to enhance operational efficiency.
Runway widening and pavement reconstruction will begin on 10 March and take approximately six weeks to complete. The runway will be closed to aircraft during this period. Stakeholders have been notified via email, but if we missed anyone, we apologise for the oversight.
Share Construction Set to Begin on Facebook
Share Construction Set to Begin on Linkedin
Email Construction Set to Begin link
20 December 2024
Upgrade works at the Tumut Aerodrome are scheduled to begin in the week starting 6 January 2025 and are expected to take approximately six months to complete.
Work will take place Monday to Friday, 7am to 6pm, and Saturdays, 8am to 4pm. Nearby residents have been notified via letter, and we apologise if anyone was missed.
While there will be increased traffic on Wee Jasper Road, all construction activity will remain within the aerodrome boundaries.
For further information, please contact Council on 1300 275 782 and ask to speak with the Project Manager, Bimal Shah.
Share Contractor Appointed on Facebook
Share Contractor Appointed on Linkedin
Email Contractor Appointed link
25 November 2024
At the November 2024 Ordinary Meeting, Council awarded a contractor to carry out the Tumut Aerodrome upgrades and work will get underway in the new year.
Upgrades include:
- Adding 90 metres to the take-off distance and 30 metres to the landing distance over the existing runway arrangement
- Improved performance / payload for emergency services operations
- Pavement strengthening
- Widening runway pavement to 23 metres for Code 2 design aircraft
- Permanent pilot activated runway lighting, making night operations possible
- Lengthen southern parallel taxiway to improve operational efficiency