May Construction Update

6 May 2026
What’s happening on site
Behind the scenes, major works continue to progress across the project:
- Electrical, mechanical, hydraulic and security rough-ins are well advanced across the Front of House and sports courts
- Roofing works are ongoing, with flashings complete and cladding progressing
- The retaining wall is now finished, marking a key structural milestone
- FOH windows are installed, with glazing now underway
- Tiered seating structural steel is in place and taking shape
- Back blocking has commenced for future fit-out works
- The mechanical platform has been installed
What to look out for in May
As works continue, you’ll start to notice:
- More of the building sealed up as glazing is completed
- Interior spaces becoming more defined with wall linings and door frames
- Visible progress in wet areas with tiling underway
- A shift from structural works to more detailed finishes