February Construction Update

12 February 2026

It’s been a busy start to the year on site, here’s the latest:

✔️ Recently completed

  • Wall panels and roof steel are now complete and certified

  • Sealing of concrete panel joints is underway

  • Concrete has been poured for the storeroom floor on the Robertson Street side, with the amenities area on the opposite side also underway

  • In-ground services have been installed, including:

    • Electrical conduits

    • Stormwater drainage

    • Water, sewer, fire and rainwater services

🔜 Coming up next

  • Roof panel installation and cladding on the sports hall

  • Steel framing for the front of house and amenities area

  • Retaining wall installation

📋 Behind the scenes
Contractors have now been secured for sporting equipment, mechanical systems, windows and glazed doors.