Construction Update

26 March 2026

What’s happening on site

Construction is continuing to move along:

  • Final building slabs poured – all slab work for the building footprint is complete.
  • Roofing installed over the sports courts, front of house, and storerooms.
  • Cladding works progressing and wall frames & trusses are now in place in the front of house.
  • Electrical, hydraulic, mechanical, and security rough-ins are in progress.
  • Steel posts for the perimeter retaining walls are being set in concrete.


What’s coming up

Here’s what’s next on site:

  • Cladding completion for the sports courts and front of house.
  • Finish rough-ins across the building.
  • Install windows, glazed doors, and door frames.
  • Add tiered seating to the sports courts.
  • Install supports for furniture, fixtures, and equipment.


The work site will be closed for the Easter long weekend from Friday 3 to Monday 6 April.